Pelagian provided a detailed GAP Analysis, cable route engineering and cable burial risk assessment consultancy services to the Rampion Offshore Windfarm.
Project work included the design and layout of the export and array cables and geospatial data management and expert recommendations for suitable cable burial equipment and techniques to inform the tendering process prior to cable installation.
The route engineering encountered challenging seabed conditions requiring the careful planning of the wind farm array cables in 20-40m of water around planned jack up locations and avoiding underlying paleochannel areas.